A suspected transmission tower vandal, arrested last year and released on bail, allegedly returned to vandalise Nigeria’s power infrastructure and has been apprehended again this time by a vigilante group in Kano State.
The suspect, identified as 35-year-old Zahradden Musa, was arrested on 18 November 2026 in Badume village, Dawakin Tofa Local Government Area of Kano State, for allegedly vandalising towers along the Kano–Gazaoúa 132kV Transmission Line.
The Transmission Company of Nigeria (TCN) disclosed this in a statement on Monday.
The TCN said the suspect is currently in the custody of the Nigeria Security and Civil Defence Corps (NSCDC), Kano State Command, for further investigation and prosecution.
According to TCN, Mr Musa was earlier arrested on March 25, 2025, for allegedly possessing stolen transmission tower members, nuts, bolts and brace components removed from Towers 91, 101, 105, 106, 107, 110, 111, 113, 114 and 115, as well as Towers 83, 86, 87 and 88 along the Kano–Kankia 132kV Line 1.
“He was subsequently released on bail but allegedly returned to vandalising transmission infrastructure.
“In his statement, the suspect reportedly admitted that he changed his name each time he was arrested to evade prosecution.
“He also confessed to vandalising several towers along the Kano–Kankia 132kV Lines 1 and 2, saying he operated at night and hid the stolen components in the bush,” the statement said.
How vigilantes caught him
TCN said Mr Musa further disclosed that three days after one of the operations, he met an accomplice, a former inmate, who was to help transport the materials to town for sale.
“Members of the vigilante group intercepted both men as they returned from the bush, arrested them and handed them over to TCN officials.
“A follow-up inspection of the transmission corridor revealed additional damage to Towers 107 and 108 along the Kano–Kankia 132kV Line 1, as well as Towers 141 and 142 along the Gazaoúa International Line,” TCN said.
TCN commended the vigilante group and the NSCDC for their vigilance and cooperation in safeguarding critical power infrastructure.
The company also appealed to the public to promptly report suspicious activities around transmission installations to security agencies or the nearest TCN office.
In recent years, vandalism has become a significant threat to Nigeria’s power infrastructure.
In May, the TCN said it recorded no fewer than 276 cases of tower vandalism between 2022 and 2025.