The federal government is set to inject an additional 480 megawatts of electricity into Ogun State’s industrial corridor with the completion of the New Abeokuta transmission substation, the flagship project under Phase 1, Batch 1 of the Presidential Power Initiative (PPI).
The Minister of Power, Joseph Tegbe, disclosed this during a high-level technical inspection of the project site in Abeokuta, the FGN Power Company (FGNPC) said in a statement by its spokesperson, Magdalene Abang, on Friday.
The inspection assessed ongoing engineering milestones aimed at transforming the existing 132/33kV facility into a modern 330/132/33kV transmission substation.
Upon completion, the statement said the project will unlock 480MW of additional wheeling capacity to power Ogun State’s rapidly expanding industrial corridor, commercial hubs and residential communities.

The PPI aligns with President Bola Tinubu’s Renewed Hope Agenda by supporting strategic investments that improve electricity access, raise industrial productivity, stimulate economic growth and strengthen Nigeria’s power sector for long-term national development.
The projects, according to the government, will strengthen Nigeria’s transmission network by increasing grid capacity, improving power evacuation and enabling more reliable electricity delivery to industrial clusters, commercial centres, businesses and households nationwide.
Phase 1, Batch 1 and 2 projects are expected to deliver an additional 4,000MW through investments in new transmission infrastructure, upgrades to existing substations and transmission lines, and expanded power evacuation capacity.
FGNPC said Siemens Energy will expand and upgrade the existing 132/33kV substation into a state-of-the-art 330/132/33kV transmission substation.
It explained that the upgrade features 2x300MVA 330/132/33kV transformers and 4x330kV and 4x132kV transmission line bays, with an associated double busbar, one-and-a-half breaker configuration.

“This will significantly improve transmission reliability and operational flexibility. In further support of the PPI’s end-to-end implementation strategy, Phase 1 projects include an associated 330kV double circuit transmission line project (Olorunsogo–Ayede Tee-Off at the New Abeokuta 330kV transmission substation).
“It ensures that increased transmission wheeling capacity can be efficiently evacuated to downstream customers while minimising stranded capacity. It also establishes a redundant, high-capacity pathway that strengthens overall grid flexibility and reliability,” the statement said.
Speaking at the inspection, Mr Tegbe said: “Today’s inspection visit marks an important milestone in the delivery of the PPI and demonstrates the unwavering commitment of President Bola Tinubu’s administration to transforming Nigeria’s power sector.
“These investments will strengthen transmission infrastructure, improve grid reliability and accelerate access to quality electricity for industries, businesses, and households across Nigeria.
“We remain committed to working with Siemens Energy and all stakeholders to deliver these projects efficiently and ensure Nigerians realise the full benefits of this transformative initiative,” he said.
Also, the Managing Director of FGN Power Company, Kenny Anuwe, said: “The PPI is a vital pillar of the federal government’s broader industrialisation and economic growth agenda.”

He said the Presidential Power Initiative is not simply an infrastructure programme, but an end-to-end intervention designed to ensure that power sector investments translate into tangible improvements in electricity delivery and economic productivity.
“Working alongside Siemens Energy and CMEC, we have already delivered 1,080MW of additional wheeling capacity under the Pilot Phase through ten power transformers and ten mobile substations. With Phase 1, Batch 1 now nearing completion, we are adding another 984MW to the national grid.”
ALSO READ: DisCos generated ₦222.86 billion in September – NERC
Mr Anuwe also highlighted the ongoing local capacity building through the PPI Seed programme to guarantee the long-term sustainability of deployed assets.
Looking ahead to 2027, FGN Power Company reaffirmed its commitment to accelerating the completion of all 16 Phase 1 transmission line projects spanning 606.5km, including the 38km Ajah–Shapaati line.
“The company will also advance contract execution and secure financing for Phase 1, Batch 2, which will deliver 12 additional substations and distribution upgrades to add 3,376MW to the national grid,” he said.